What this covers
|
Every small project has the same post-mortem. One thing arrived late, and somehow the whole plan moved by more than that one thing was late by.
That is not bad luck and it is not padding that got used up. It is a structural property of how schedules are built, and once you can see it, it is largely avoidable.
A Delay Is Not Additive
A plan is a chain of dependencies, not a list of durations. Task C cannot start until B finishes, and B cannot start until A finishes.
When A slips by one day, three separate things happen.
- The direct push. Everything downstream moves one day
- The resource collision. The crew booked for B on Tuesday is now needed on Wednesday, but Wednesday was already committed elsewhere. That is not one day, it is however long until they are free again
- The calendar effect. A one-day slip into Friday afternoon becomes a three-day slip, because Saturday and Sunday do not absorb work
The second and third are what turn one day into four. Neither appears anywhere on the plan.
Where Slack Usually Sits, and Where It Should
Most small plans carry slack in two places: inside each task, and in a lump at the end.
Both are weak. Slack inside a task gets absorbed, because work expands to the time available and nobody reports finishing early. Slack at the end protects the final date but does nothing for the chain, so the collisions still happen one by one on the way there.
Slack is better placed immediately before the points where many things converge, and immediately after anything you do not control.
|
Place |
What it protects against |
Worth it? |
|
Inside every task |
Nothing, it gets absorbed |
No |
|
One lump at the end |
The final date only |
Weak |
|
Before a convergence point |
Several chains arriving at once |
Yes |
|
After an external dependency |
Deliveries, inspections, approvals |
Yes |
|
Around a shared resource |
Collisions you cannot resolve on the day |
Yes |
Identify What You Do Not Control
The tasks that cause compounding delays are almost always the ones owned by somebody else: a delivery, an inspection, a permit, an approval, a specialist trade with their own book.
List them. For each, ask two questions. How late can this be before something downstream cannot start? And what is the fallback if it is later than that?
Often the fallback is simply ordering earlier, which costs nothing but attention. Sometimes it is sequencing so that the uncontrolled item is not sitting in the middle of the chain.
Convergence Points Deserve Protection
The riskiest moment on any plan is where several chains have to arrive together: the site has to be clear, the material has to be there, and the crew has to be free, all on the same morning.
A convergence point fails if any one of its inputs is late, so its probability of slipping is much higher than that of any single input. Those are the places that earn a buffer.
On a renovation, the classic convergence point is the moment finishing work starts. It needs the demolition done, the debris gone, the inspection passed and the material delivered. Three of those four are frequently late, and the fourth, debris removal, is the one most often not even on the plan.
The Task Nobody Schedules
Debris handling is a dependency like any other. It has a duration, it needs a resource, and several downstream tasks cannot start until it is done. It just rarely gets written down, because no invoice marks it.
The result is that it becomes the unplanned task sitting directly in front of the most important convergence point on the job. That is the worst possible position for something nobody is tracking.
Writing it on the plan costs nothing. Booking the container one working day before tear-out, rather than the morning of, removes an entire class of slip.
Run a Five-Minute Pre-Mortem
Before the plan is locked, ask one question: if this runs two weeks over, what happened?
The answers come quickly and they are almost always the same three or four items. Those are your uncontrolled dependencies and your convergence points. Put the buffers there, and order the long-lead items that day.
It takes five minutes and it is worth more than any amount of re-sequencing later.
Track the Chain, Not the Tasks
A task list tells you what is done. A dependency chain tells you what is at risk. The useful daily question is not “what did we finish” but “what is the next thing that cannot start, and is its input on track”.
For projects around Springfield, Missouri, Roll-Off Express covers container rental across the city and the surrounding counties. You can look at the options here, and their page on coverage on the east side of Springfield shows how the area breaks down. The company keeps a Google Business Profile.
Put the buffer before the convergence, order the uncontrolled items early, and write down the tasks that nobody invoices for. Those three habits absorb most of what turns one late day into four.